The Purple Line
The Purple Line of Dankal starts at the eastern parts of the metropolitan area, through Ramat Gan and Givatayim , and arrives to the heart of Tel Aviv
- 256,000Daily Passengers
- A Trainevery 4 minutes
- 2026Opening Year
Line Progress
2018
2027
-
December 2018 Start of infrastructure works -
March 2021 Ben Yehuda works -
January 2022 Kfar Shalem works -
January 2022 Winning bids announced -
July 2023 Infra 2 works
Purple Line Stations
- Length27 Km
- stations43
- cities6